Sprint Pulse

Product Pulse — Team-2 ADS Q2 W23 - 08-12 June

Planned sprint ADS Q2 W23 - 08-12 June • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 6 of 15 visible items, including 3 Stories, 1 Tasks, and 2 Bugs. Product movement was real, but the sprint was still noisy: 5 items entered after planning and 2 of them were closed. The main misses were concentrated in 9 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items15Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items6Items whose final outcome bucket is Done
Carry overs9Items not closed at sprint review
Delivered mix3 / 1 / 2Stories / Tasks / Bugs delivered
Entry kind mix10 / 5 / 0Planned / Added during sprint / Stretch visible
Readiness mix6 / 9 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended1/2Progress items were expected not to finish in this sprint

Capacity context

SignalValueHow to read it
Available capacity67.2Policy-weighted engineering availability after holidays and OOO
Nominal capacity68Active workdays after weekends and bank holidays, before OOO
OOO capacity0.8Vacation / OOO days from tracker evidence when present
Bank holiday capacity0Policy-weighted public-holiday capacity removed from the sprint window
Included people18People with non-zero implementation capacity in this sprint window

Capacity is companion context for the pulse; it does not alter snapshot issue-count denominators.

It is not a true hours estimate.

OOO tracker export: capacity_ooo_tracker_export.csv

Pavel Petronel replaced Dron Gabriel

Paul Tanasuca ended without configured replacement

Rojan Shrestha replaced Raul Popovici

Stories done (3)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-7284 — Refactorizare "Anuleaza recurenta"Planned
ADS-7427 — [Admitere v2][Taxe] - 3. Admin Vizualizare/Validare platăPlanned
ADS-7428 — [Admitere v2][Taxe] - 4. Candidate - Necesita modificăriPlanned

Tasks done (1)

Jira itemHow entered
ADS-7423 — [Stiri] - Updates after release/feedbackPlanned

Bugs done (2)

Jira itemHow entered
ADS-7743 — [FE/BE] - Bugs Admitere v3Added
ADS-7773 — [BE][UPA-Admitere] - BugsAdded

Carry overs / not delivered (9)

Jira itemWhy it carried
ADS-1757 — Story — [Financiar] - Plati partialeDependency delay
ADS-6494 — Story — Log levels & Log formatsDependency delay
ADS-7239 — Story — [Admitere v2] - Label/eticheta cazuri specialePartial completion
ADS-7405 — Story — [BE] - Local CacheDependency delay
ADS-7430 — Story — [Admitere v2][Taxe] - 5. Export platile candidatului&extinderea cu alte informatii ale candidatilorNot started
ADS-7487 — Story — [Admitere v2] - Adaugare candidat in billing&eliberare chitantaPartial completion
ADS-7519 — Task — [BE] "Afișează noutăți Adservio" toggle is non-functionalDependency delay
ADS-7849 — Story — Stergere date S3Partial completion
ADS-7874 — Task — [Node/React] Cache images for news created by admins via CDNPartial completion

Blocker / miss pattern

MetricValueHow to read it
Partial completion1Carryovers blocked by partial completion
Dependency / competing work4Delivery slipped because attention or dependency landed elsewhere
Not started1Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

1 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1111 issues in the planning snapshot
Sprint review / outcome snapshot raw list1515 issues in the Friday review snapshot
Normalized sprint fact base1515 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.