Executive summary

Yellow. The sprint closed 7 of 16 visible items, including 2 Stories, 3 Tasks, and 2 Bugs. Product movement was real, but the sprint was still noisy: 4 items entered after planning and 1 of them were closed. The main misses were concentrated in 9 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items16Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items7Items whose final outcome bucket is Done
Carry overs9Items not closed at sprint review
Delivered mix2 / 3 / 2Stories / Tasks / Bugs delivered
Entry kind mix11 / 4 / 1Planned / Added during sprint / Stretch visible
Readiness mix5 / 9 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended2/3Progress items were expected not to finish in this sprint

Capacity context

SignalValueHow to read it
Available capacity50Policy-weighted engineering availability after holidays and OOO
Nominal capacity54.4Active workdays after weekends and bank holidays, before OOO
OOO capacity4.4Vacation / OOO days from tracker evidence when present
Bank holiday capacity13.6Policy-weighted public-holiday capacity removed from the sprint window
Included people18People with non-zero implementation capacity in this sprint window

Capacity is companion context for the pulse; it does not alter snapshot issue-count denominators.

It is not a true hours estimate.

OOO tracker export: capacity_ooo_tracker_export.csv

Pavel Petronel replaced Dron Gabriel

Paul Tanasuca ended without configured replacement

Rojan Shrestha replaced Raul Popovici

Stories done (2)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-7132 — [FE/BE] - Gestiunea restantierilorPlanned
ADS-7476 — [UNI][MAIN][Plan invatamant] - Teste automate Plan invatamant (adaugare, editare, import) E2EPlanned

Tasks done (3)

Jira itemHow entered
ADS-7472 — [FE/BE][UNMB] - Actualizare a structurii (serii, grupe) astfel încât afișarea să respecte ordinea din fișierele transmisePlanned
ADS-7635 — [FE/BE][UNMB] - Posibilitatea introducerii notelor cu zecimalePlanned
ADS-7729 — Îmbunătățirea procesului pentru import Excel studenți V2Planned

Bugs done (2)

Jira itemHow entered
ADS-7742 — [FE/BE][Cazari] - Filtrul dupa camera si camin nu returneaza studentiiPlanned
ADS-7751 — [BE][Catalog- Note discipline-Asachi] - Notele introduse nu sunt afișate, iar în catalog apare valoarea „null”Added

Carry overs / not delivered (9)

Jira itemWhy it carried
ADS-7375 — Story — [BE/FE] - Disciplinele in EN pentru programele de studiu din ENPartial completion
ADS-7388 — Bug — docgen2-api: gradebook view/download endpoints return HTTP 500 - 15 hits/FridayNot started
ADS-7495 — Story — [FE/BE][Adeverinte absolvire] - Creare Probe evaluarePartial completion
ADS-7496 — Story — [FE/BE][Adeverinte absolvire] - Probe&medie pe situatie scolaraPartial completion
ADS-7534 — Story — [FE/BE][Adeverinte absolvire] - Flow generare adeverintePartial completion
ADS-7666 — Bug — accommodations-api: shared HTTP 500 burst on POST /api/v2/accommodations/dorms/list and related endpoints - 16 hits/20mBug / rework pressure
ADS-7688 — Bug — [BE] [Studenti] [Muzica]- Studentul nu este unificat pe baza CNP-ului la importNot started
ADS-7708 — Bug — [BE] - Personal universitar: Numele nu se actualizeaza corect dupa editareNot started
ADS-7740 — Story — [TDD][Generare Adeverințe] - Creare document tehnicNot started

Blocker / miss pattern

MetricValueHow to read it
Partial completion3Carryovers blocked by partial completion
Dependency / competing work0Delivery slipped because attention or dependency landed elsewhere
Not started2Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

2 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list1212 issues in the planning snapshot
Sprint review / outcome snapshot raw list1616 issues in the Friday review snapshot
Normalized sprint fact base1616 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.