Product Pulse — University ADS Q3 W28 - 13-17 Jul

Planned sprint ADS Q3 W28 - 13-17 Jul • planning snapshot + end-of-sprint outcome snapshot

This retrospective uses the planning snapshot as the baseline promise set for sprint intent and entry kind, and the outcome snapshot as the actual end-of-sprint result.

Download DOCX

Executive summary

Yellow. The sprint closed 11 of 23 visible items, including 6 Stories, 3 Tasks, and 2 Bugs. Product movement was real, but the sprint was still noisy: 4 items entered after planning and 1 of them were closed. The main misses were concentrated in 12 carryovers.

Top-line metrics

MetricValueHow to read it
Visible sprint items23Normalized sprint fact base: planning baseline plus outcome additions and planning-only misses
Delivered items11Items whose final outcome bucket is Done
Carry overs12Items not closed at sprint review
Delivered mix6 / 3 / 2Stories / Tasks / Bugs delivered
Entry kind mix19 / 4 / 0Planned / Added during sprint / Stretch visible
Readiness mix5 / 18 / 0Ready / At risk / Not Ready across the normalized sprint fact base
Progress items behaving as intended3/6Progress items were expected not to finish in this sprint

Stories done (6)

Below are the items marked Done in the sprint review snapshot, grouped by work-item type.

Jira itemHow entered
ADS-7495 — [FE/BE][Adeverinte absolvire] - Creare Probe evaluarePlanned
ADS-7496 — [FE/BE][Adeverinte absolvire] - Probe&medie pe situatie scolaraPlanned
ADS-7778 — [ANMGD] - Onboarding Academia Nationala de Muzica "Gheorghe Dima" - Cluj-NapocaAdded
ADS-7952 — [Burse] - US1 - Implementare mecanism AtributePlanned
ADS-7958 — [FE/BE] - Reconstituire scolaritate - transfer, an repetarePlanned
ADS-8055 — [Asachi][FE] - Salvarea pe cataloage sa se faca pe toate paginile nu pe fiecare pagina in partePlanned

Tasks done (3)

Jira itemHow entered
ADS-8073 — [FE/BE] - Aducerea titularilor din planul curent in tab-ul restantieri pe disciplinaPlanned
ADS-8141 — [FE][Situatie scolara] - Lipsa mesaj de eroare la modificarea mediei de absolvirePlanned
ADS-8188 — Extindere import studenti cu coloana sectiePlanned

Bugs done (2)

Jira itemHow entered
ADS-8111 — [FE/BE] - In centralizator note nu apare numele unei disciplinePlanned
ADS-8271 — [Prod][AWS][uni-api] Auth bootstrap race returns 401 after duplicate local-user insert - 1 request/72hPlanned

Carry overs / not delivered (12)

Jira itemWhy it carried
ADS-6142 — Story — [Registre Matricole] -US1.1 Creare volume si asociere studenti incadratiPartial completion
ADS-6438 — Task — [BE][UNI] - Sincronizare ID-uri Ani universitari/scolari - UNI/preuni - masterPartial completion
ADS-7534 — Story — [FE/BE][Adeverinte absolvire] - Flow generare adeverintePartial completion
ADS-7535 — Story — [FE] - Download Adeverinta de absolvireDependency delay
ADS-7666 — Bug — accommodations-api: shared HTTP 500 burst on POST /api/v2/accommodations/dorms/list and related endpoints - 16 hits/20mBug / rework pressure
ADS-7890 — Story — [BE PHP][Cazari] - Stingerea obligatiilor din E-taxeDependency delay
ADS-8104 — Story — [BE-PHP] - Gestiunea cazarilor de varaDependency delay
ADS-8118 — Bug — [BE] - Lipsa nota si catalog deschis pe restantieriNot started
ADS-8147 — Bug — [BE] - Nu apar studentii pe sesiunea 2Not started
ADS-8153 — Bug — [Prod][TUIASI][accommodations-api] Student balance export returns HTTP 500 when mPDF hits pcre.backtrack_limitNot started
ADS-8186 — Bug — [Prod][AWS][accommodations-api] External person create returns 500 after partial create when fallback faculty is hidden by scopeBug / rework pressure
ADS-8244 — Bug — [Cazari] - Sold gresit in obligatie de plata fata de fisa studentuluiNot started

Blocker / miss pattern

MetricValueHow to read it
Partial completion3Carryovers blocked by partial completion
Dependency / competing work3Delivery slipped because attention or dependency landed elsewhere
Not started4Committed item never really got underway

Data-quality caveats

This product pulse is retrospective only and uses the planning snapshot for baseline fields and the outcome snapshot for actuals.

3 rows have Sprint Intent = Progress and remained open; they are treated as healthy continuation rather than finish misses.

Traceability / drill-down

Report elementHow to drill downTraceability mechanism
Delivered Stories / Tasks / BugsClick the section count rowsSnapshot-exact JQL by issuekey list
Carry overs / not deliveredClick the Carry overs countSnapshot-exact JQL by issuekey list
Miss pattern summaryClick each miss-pattern countSnapshot-exact JQL by issuekey list

Snapshot and fact-base list links

SnapshotIssue countLink
Planning snapshot raw list2020 issues in the planning snapshot
Sprint review / outcome snapshot raw list2323 issues in the Friday review snapshot
Normalized sprint fact base2323 issues used for metrics and drill-down

Planning and outcome are separate frozen moments.

Metric tables use the normalized sprint fact base, which keeps planning-only misses and outcome-only additions visible for traceability.

Evidence artifacts

ArtifactLink
Issue audit registerOpen issue-level audit CSV
Metric lineageOpen metric lineage CSV
JQL traceability registerOpen JQL traceability CSV
Sprint metrics JSONOpen sprint metrics JSON

Use these files when you need to validate the exact rows and formulas behind a pulse claim.